1. Background, Historical Context & Rationale
1.1 Why PPP Was Needed
•
National
treasury alone insufficient to fund infrastructure (roads, bridges, airports,
railways, electricity, irrigation, cable cars, drinking water)
•
PPP
attracts private sector means, resources, skills and technology for public
development works
•
Private
sector contributes: managerial expertise, innovative technology, and capital
investment
•
Goal:
make public assets and services less costly, effective and reliable
1.2
Legislative Timeline
•
2000 2000 AD -
"Construction, Operation and Handover of Public Infrastructure
Policy" formulated
•
2006 2006 AD -
"Private Sector Investment in the Construction and Operation of
Infrastructure Act" enacted; still in force
• 2015 2015 AD - PPP Policy 2072 (new policy) formulated; repeals the 2000 policy
1.3
Nepal's Development Status (2015 Baseline)
Nepal aimed to graduate from Least Developed Country (LDC) to developing country by 2022 AD.
|
Indicator |
Nepal Status (2015) |
LDC Target / Goal |
|
GNI
per capita (actual) |
USD
659 |
USD
1,242 |
|
Human
Asset Index |
68.7 |
66
(threshold) |
|
Economic
Vulnerability Index |
26.8 |
32
(threshold) |
|
Infrastructure
investment (% GDP) |
3-4% |
6-7%
growth target |
|
Required
investment by 2022 |
- |
~Rs.
10,000 billion |
1.4 Key Challenges
•
Enhancing
investment and management capacity in infrastructure sector
•
Private
sector unable to meet time-bound responsibilities (land acquisition,
coordination, environmental approval)
•
Limited
resources and weak professional competence in PPP implementation
•
Absence
of policy on proper risk-sharing for large national infrastructure projects
•
No
proper Viability Gap Funding (VGF) arrangement
•
Non-transparent
project selection process; inadequate feasibility studies
•
Lack
of independent appraisal practices for feasibility studies
•
Persistent
security problems and land acquisition difficulties
• Policies not in tune with current international norms and practices
|
Key Fact: Nepal needed approximately Rs. 10,000 billion in investment
by 2022 AD to achieve the required growth in infrastructure. Current
infrastructure investment of 3-4% of GDP was insufficient; 6-7% annual
economic growth was targeted. |
2. Vision, Goal & Objectives
2.1
Vision
|
"To ensure public access to infrastructure and services
through their qualitative and sustainable development." |
2.2
Goal
|
"To enhance public-private sector investment on
development and operation of public infrastructure services through the
adoption of the PPP model for comprehensive socio-economic development." |
2.3
Objectives (Clause 8)
•
8.1 Clause 8.1 - Create environment
attracting private investment (domestic and foreign) to meet capital and
resource requirements for development, reconstruction and operation of public
infrastructure
• 8.2 Clause 8.2 - Utilize professionalism, work efficiency, entrepreneurship and technical skills of private sector for qualitative public infrastructure services
3. Policies & Strategies
3.1
Three Core Policies (Clause 9)
•
9.1 Policy 9.1 - Promote PPP-related
international norms and standards in all feasible state organs and entities
•
9.2 Policy 9.2 - Create conducive
investment environment for domestic and foreign private sector in
infrastructure development
•
9.3 Policy 9.3 - Optimal utilization
of private sector professionalism, entrepreneurship, ability and latest
technologies
3.2
Strategies (Clause 10)
For
Policy 9.1 (Clauses 10.1-10.3)
•
Accept
and adopt prevailing PPP norms in all possible public sectors on basis of
necessities and relevance
•
Identify
and prioritize infrastructure and services implementable under PPP concept
•
Make
all state organs vibrant as needed to implement PPP projects
For
Policy 9.2 (Clauses 10.4-10.6)
•
Make
procurement and approval processes simple and transparent
•
Share
risks and benefits between public and private sectors in a justifiable manner
•
Ensure
GoN investments, cooperation and commitments to implement PPP and boost private
sector morale
For
Policy 9.3 (Clauses 10.7-10.9)
•
Use
private sector competence in identification, prioritization, feasibility study
and framework preparation
•
Utilize
professionalism and entrepreneurship of private sector in construction and
management
•
Ensure
accountability of private sector for sustainable operation, repair and
maintenance
4. Underlying PPP Principles & Project Forms
(Clause 11.1)
4.1
Defining Characteristics of a PPP
•
Fixed-period
contract between public and private entities
•
Private
entity bears full or partial financial/construction/operation/maintenance risks
•
Private
entity provides public services directly or indirectly
•
Return
on investment through user fees collected over the concession period
• Assets must revert to public entity ownership after the contract period ends
4.2
Salient Features Required (Clause 11.1(5))
•
Clearly
defined contract period
•
Full
or partial private capital investment for
construction/rehabilitation/modernization
•
Private
entity responsible for operation, maintenance and service delivery
•
Performance-linked
payment benchmarks set in advance
•
Private
entity accepts income-related risk (partly or fully)
•
All
provisions formalized in a duly signed project agreement
4.3
What Does NOT Constitute a PPP (Clause 11.2(ii))
•
Services
operated by private sector without transferring financial, technical or
operational risks
•
Privatization
of public assets or liabilities
•
Commercialization
of public works through government-owned enterprises created by government
decision
•
Receipt
of grants, donations or gifts from private entities for public works
•
State
security provisions
4.4
Forms of PPP (Spectrum - Minimal to Maximum Private Involvement)
•
Management/Operation
Contract - private operates public asset, no investment, no risk transfer
•
Lease
/ Concession Agreement - private operates public asset, pays royalty/rent
•
Build-Operate-Transfer
(BOT) / Build-Own-Operate-Transfer (BOOT)
•
Design-Build-Operate-Transfer
(DBOT)
•
Full
private investment with eventual ownership transfer - maximum private
involvement
Suitability determined by: project
structure, investor/lender acceptability, user fee viability, risk-benefit
sharing, and defined agreement period.
4.5
Requirements for Project Implementation (Clause 11.2(i))
•
Clear
provision on user fees or performance payment mechanism
•
Clear
allocation of responsibilities between public and private entities
•
Risk
borne by entity most capable of bearing it
•
Detailed
service specifications, payment benchmarks, incentives, penalties and grievance
mechanisms
•
Clarity
on ownership of existing and newly created assets
•
Effective
monitoring system at every level of project cycle
• Result-based payment, motivational incentives and penalty provisions
5. Priority Sectors & Project Identification
(Clause 11.3)
5.1
National Priority Sectors
•
Physical
infrastructure and transportation - Roads, Bridges, Airports, Railways, Cable
Cars, Ropeways, all ports
•
Electricity
sector - Generation, transmission and distribution (together or separately) and
other energy types
•
Information
and communication sector
•
Urban
and rural environment - Solid waste management, drinking water, sewerage and
sanitation
•
Education,
health infrastructure, and tourism infrastructure (excluding hotels and
accommodation)
• Urban amenities
|
Important: Local level PPP projects do NOT require their own
specific prioritization list. Techno-economic and market feasibility are the
deciding parameters for local level projects (Clause 11.3(3)). |
5.2
Project Selection Criteria
•
Quality
and access to services enhanced
•
Current
public service status improved
•
Economic
benefit to Nepalese economy ensured
•
Government
and local entity funds effectively mobilized
•
Innovative
and high-level technology utilized
5.3
Project Identification Process (Clause 11.4)
•
All
public entities identify and determine priority areas; may hold consultation
meetings with private sector
•
PIAs
select, design and assess suitability of PPP projects from identified areas
•
PIAs
furnish identified projects to National Planning Commission (NPC) for analysis
before proceeding
•
For
projects below Rs. 50 million - chief executive of public entity may formulate
own procedures
• Private sector interested in developing a project may be invited to do so (Clause 11.4(4))
6. Project Appraisal & Procurement Process
(Clauses 11.6 & 11.7)
6.1
Approval Before Procurement (Clause 11.6)
•
Procurement
process can only commence after: feasibility study, suitability appraisal, and
procurement document approval by competent authority
•
PIA
submits feasibility study, procurement documents, bidder details and preferred
competitor details to approving authority before signing project agreement
•
Approving
authority may ask PIA to revise project structure or grant approval with
mandatory conditions
•
Any
changes to approved documents or project outlay require fresh approval from
competent authority
6.2
Six-Step Procurement Process (Clause 11.7)
Step 1: REOI — Request for
Expression of Interest - optional stage to gauge market interest, understand
prospective bidders and associated risks
Step 2: RFQ — Request for
Qualification - evaluate overall technical and financial competency; prepare shortlist
of qualified bidders
Step 3: RFP — Request for
Proposal - detailed technical and financial proposals invited from shortlisted
bidders only; project agreement draft included
Step 4: Evaluation — Committee
(including PPP Centre, NPC and MoF representatives) evaluates proposals on
predetermined criteria; technical and financial proposals opened at different
times
Step 5: Bid Approval — Preferred
bidder's proposal approved by competent authority; notification letter issued
Step 6: Agreement
Signing — Project
agreement signed; no substantive changes from RFP draft; only minor
administrative matters may be amended
6.3
Key RFP Provisions (Clause 11.7(C))
•
Project
period and specifications clearly stated
•
Monitoring
process and compensation provisions
•
Methods
for resolving force majeure, contract termination and scope changes
•
VGF
and/or equity provisions; royalty/rent/lease charge details
•
Risk
sharing and management methods during project period
•
Infrastructure
handover process
•
Bid
security required with proposal; performance guarantee required before
agreement
• Financial proposals opened only for technically qualified bidders
6.4
Unsolicited Proposals (Clause 11.8)
An unsolicited proposal is one not
invited by PIA but identified and submitted by an interested private entity.
•
Accepted
only under three specific conditions:
◦
(a)
Proposals were invited earlier but a successful bidder could not be selected
◦
(b)
Project uses proprietary goods available only with that particular entity
◦
(c)
Council of Ministers declares the project strategically important
•
Projects
above Rs. 100 million require Council of Ministers approval in principle before
proceeding
•
If
project accepted for processing - PIA invites competitive bids; proposer may
also participate
•
Proposer
has 30 days to match preferred bidder's commitments; if accepted, preferred
bidder compensated for bid preparation costs
•
If
proposer declines or fails to qualify - project not awarded to proposer
7. Key Financial Thresholds
|
Threshold |
Provision |
|
Below Rs. 50 million |
Chief
executive of public entity may formulate and implement own PPP procedures
independently (Cl. 11.4(8)) |
|
Below Rs. 100 million |
PIA
may decide itself whether to seek PPP Centre appraisal; single-stage RFQ+RFP
process allowed (Cl. 11.7(2)(a)) |
|
Rs. 100 million and above |
Mandatory
submission to PPP Centre for suitability appraisal; model documents must be
used (Cl. 11.6(1)(b)) |
|
Rs. 500 million+ OR requires VGF/grants |
PPP
Board of Directors approval required before commencing procurement (Cl.
11.6(3)(c)) |
|
Above Rs. 1 billion |
International
bids mandatory (Cl. 11.7(2)(d)) |
|
Land acquisition |
Project
agreement cannot be signed unless 80% of required land is acquired by GoN
(Cl. 11.9(5)) |
|
Unsolicited proposals above Rs. 100 million |
Council
of Ministers approval in principle required before processing (Cl. 11.8(5)) |
7.1
Approving Authority Summary
•
National-level
PIA, below Rs. 500 million, no VGF required - PIA chief executive grants
approval
•
Rs.
500 million+ and/or requires VGF or government grants - PPP Board of Directors
approval required
•
Local
body, no VGF, no central grant - local body approves and implements
independently
•
Local
body, requires VGF or central government financial support - PPP Board of
Directors approval required
•
Investment
Board Nepal as PIA - follows Investment Board Act; Board of Directors only for
VGF/central grant cases
8. Institutional Framework (Chapter 12)
8.1
PPP Board of Directors (Clause 12.1)
•
Chairperson:
Secretary, Ministry of Finance
•
Members:
Secretaries of PMO, NPC Secretariat, Home Affairs, Physical Infrastructure
& Transport, Land Reform, Forestry, Science/Environment, concerned
Ministry, Federal Affairs & Local Development
•
Member
Secretary: Chief, PPP Centre
Scope
of Work
•
Provide
guidelines on all PPP-related policy matters
•
Identify
areas and investment opportunities for PPP projects
•
Grant
approval for procurement process for Rs. 500m+ projects and those requiring VGF
•
Establish
necessary coordination with concerned entities
8.2
PPP Regulatory Committee (Clause 12.2)
•
Chairperson:
Secretary, National Planning Commission
•
Members:
Joint secretaries of MoF, Home Affairs, Physical Infrastructure, Federal
Affairs, Land Reform + appointed expert; PPP Centre chief as Member Secretary
•
Submits
annual report to NPC through infrastructure sector member
•
NPC
may carry out review and issue necessary directives
8.3
PPP Centre (Clause 12.3)
•
Located
under National Planning Commission
•
Functions:
feasibility study and independent suitability appraisal; facilitation of public
and private entities; PPP capacity building; domestic and international best
practice research; model documents and guidelines; investor/bank coordination;
maintain contingent liability records
•
Issues
model documents: RFQ, RFP and project agreement templates
•
Must
be consulted before implementing innovative, complex or debut PPP projects
8.4
PIA & PIU (Clause 12.4)
•
Every
public entity implementing PPP projects = Project Implementing Agency (PIA)
•
Each
PIA forms a Project Implementation Unit (PIU) per individual project
•
PIU
responsibilities: preparatory works, studies, procurement, coordination,
agreements with private entities, implementation
•
Investment
Board Nepal: hands approved projects to concerned Ministry after financial
closure
9. Financial Provisions (Chapter 13)
9.1
Four Key Financial Instruments
(a) Project Preparation Facility Fund (PPFF) -
Clause 13.4
•
Established
by Ministry of Finance
•
Purpose:
feasibility studies, consultancy services, analysis of challenges and
opportunities of PPP projects
•
Management
and mobilization governed by dedicated manual
(b)
Revolving Fund for Land Acquisition (RFLA) - Clause 13.5
•
Established
by Ministry of Finance
•
GoN
acquires land for PPP projects; costs recoverable from private sector through
royalty/rent/lease fee/compensation
•
Recovered
amounts re-deposited in RFLA (revolving nature)
(c)
Viability Gap Fund (VGF) - Clause 13.6
•
Established
by Ministry of Finance
•
Provides
direct capital grants to make financially unviable but publicly important
projects viable
•
Conditions:
financial income insufficient to meet expenses AND no adequate alternative
funding exists
•
Board
of Directors decides on VGF grant on recommendation of PPP Centre
•
NOT
applicable to projects receiving annual installment payments from PIA
(d)
Capital Participation - Clause 13.7
•
PIAs
may invest equity in PPP projects in special cases with clear documented
justification
• Bases: enhancing financial viability, strong PIA presence, investor-friendly environment, reasonable project monitoring
9.2
Who Bears Which Costs (Clause 13.10)
•
Government:
administrative processes (project selection, feasibility study, supervision,
expert identification), initial land acquisition costs
•
Private
sector: all financial obligations related to project implementation
•
Public
entity: PIU administrative costs
•
Land
acquisition costs initially by GoN; recoverable from private sector through
royalty/rent/lease/reimbursement
•
Tax
exemption/waiver by GoN permissible depending on project nature (Clause 13.8)
9.3
Budget Provisions (Clause 13.1)
•
National
level: PIA proposes budget to MoF and NPC; MoF takes final decision in
consultation with NPC and PIA
•
Local
body as PIA: local body council decides budget; included in its budget book
• PPP Centre administrative and other expenses included in every annual budget
10. Risk Sharing, Disputes, Monitoring &
Handover
10.1
Risk Sharing Principles (Clause 11.10)
|
Central Principle: 'Public interest' is kept at the centre.
The entity most competent to manage a particular risk should bear that risk.
Risk sharing framework based on feasibility study and opportunity analysis. |
|
Risk Type |
Assigned To |
|
Design,
construction, project management quality, technical standards |
Private entity |
|
Environmental
regulation compliance |
Private entity |
|
Cost
of service, financial management, fee recovery, profit |
Private entity |
|
Permissions,
approvals and inter-government coordination |
PIA (public entity) |
|
Land
acquisition |
PIA (public entity) |
|
Government
grants-related risks |
PIA (public entity) |
|
Force
majeure (direct/indirect) |
Insurance first; uninsured matters per project agreement |
|
Asset
transfer / contract void or cancelled |
Adjusted per project agreement; burden depends on cancellation
reason |
10.2
Land Acquisition (Clause 11.9)
•
GoN
provides required land to PIA for PPP projects at national and local levels
•
GoN
follows prevailing land acquisition laws and Land Acquisition, Rehabilitation
and Resettlement Policy 2014
•
Compensation
against land acquisition may be reimbursed through private entity (fully or
partly) as stated in procurement documents
•
Critical
Rule: Project agreement CANNOT be signed unless GoN has acquired 80% of the
required land
10.3
Dispute Settlement (Clause 11.12)
•
First:
Prevailing Nepal laws apply to project agreement
•
Second:
Amicable settlement through dialogue and discussion between disputing parties
•
Third:
If amicable settlement fails - Arbitration Act, 1999 applies
•
For
foreign investors: ICC Rules or UNCITRAL dispute resolution procedure may be
adopted (must be stated in project agreement)
•
Special
projects: separate provisions by Council of Ministers decision as stated in
agreement
10.4
Monitoring & Evaluation (Clause 15)
•
Primary
responsibility: concerned public entity through PIU
•
MoF
(with PPP Centre) may constitute working committees for financial climate
review
•
PPP
Centre submits annual report to GoN through Board of Directors - must report
results achieved and problems faced
•
Private
entity submits annual audit reports on PPP project income and expenditure to
public entity
10.5
Project Handover (Clause 18)
•
On
contract expiry: private entity hands over physical infrastructure and assets
in running condition to PIA
•
One
year before handover: repair and maintenance under PIA supervision as guided by
project documents
•
PIA
deputes its representatives to oversee the handover process
10.6
Regulatory Provisions (Clause 16)
•
GoN
constitutes separate sector-specific regulatory bodies
•
Regulatory
bodies regulate PPP projects
• If no regulatory body exists: regulation based on non-discrimination, independence, transparency and accountability
10.7
Policy Implementation Plan (Clause 11.11)
•
This
policy acts as the base for formulating Acts, rules, guidelines and manuals
•
Within
one year of approval: GoN to develop manuals for PPFF and VGF; PPP Centre to
issue model documents
• Local bodies to amend the "Public Private Partnership (For Local Bodies) Policy, 2003" on the basis of this policy
11. Quick Reference Summary for Exam
|
Repeal & Saving (Clause 19): The "Public
Infrastructure Construction, Operation and Handover Policy, 2000" is
repealed. All actions taken under the 2000 policy are deemed to have been
taken under the 2015 policy. |
11.1
Five Key Numbers to Memorize
•
Rs.
50 million - threshold below which PIA chief executive has autonomous authority
•
Rs.
100 million - threshold requiring mandatory PPP Centre appraisal and model
documents
•
Rs.
500 million - threshold requiring PPP Board of Directors approval
•
Rs.
1 billion - threshold requiring international bids
•
80%
- minimum land acquisition by GoN required before signing project agreement
11.2
Key Definitions
•
PPP
Centre: Under NPC; responsible for appraisal, model documents, capacity
building, guidelines
•
PIA
(Project Implementing Agency): Any public entity implementing a PPP project
•
PIU
(Project Implementation Unit): Unit formed by PIA per project for
implementation
•
VGF
(Viability Gap Fund): Capital grant to make financially unviable but publicly
important projects viable
•
Unsolicited
Proposal: Proposal not invited by PIA but submitted voluntarily by private
entity
•
REOI:
Request for Expression of Interest (optional, first stage of procurement)
•
RFQ:
Request for Qualification (Stage 1 - evaluates technical/financial competency,
produces shortlist)
•
RFP:
Request for Proposal (Stage 2 - invites full technical and financial proposals)
11.3
Important Policy Principles
•
PPP
is a time-bound contract - not permanent privatization
•
Assets
always revert to public entity after contract period
•
Risk
borne by entity most capable of managing it
•
Public
interest is central to all risk/benefit sharing decisions
•
Feasibility
study and suitability appraisal are mandatory before procurement
•
No
project agreement can be signed without 80% land acquisition by GoN
•
International
arbitration (ICC/UNCITRAL) available for foreign investor disputes
• GoN may provide tax exemptions for PPP projects depending on nature and characteristics
|
These notes are based on the unofficial English translation of
Nepal's Public-Private Partnership Policy, 2072 (2015). For official
reference, consult the original Nepali version published by the Ministry of
Finance, Government of Nepal. |
Comments