Online destination for education

April 25, 2026

Public-Private Partnership (PPP) Policy 2072: Structure, Process, and Implementation in Nepal

Public-Private Partnership Policy, 2072 (2015)

1. Background, Historical Context & Rationale

1.1 Why PPP Was Needed

      National treasury alone insufficient to fund infrastructure (roads, bridges, airports, railways, electricity, irrigation, cable cars, drinking water)

      PPP attracts private sector means, resources, skills and technology for public development works

      Private sector contributes: managerial expertise, innovative technology, and capital investment

      Goal: make public assets and services less costly, effective and reliable

Public-Private Partnership Policy, 2072 (2015)

1.2 Legislative Timeline

      2000 AD - "Construction, Operation and Handover of Public Infrastructure Policy" formulated

      2006 AD - "Private Sector Investment in the Construction and Operation of Infrastructure Act" enacted; still in force

      2015 AD - PPP Policy 2072 (new policy) formulated; repeals the 2000 policy

1.3 Nepal's Development Status (2015 Baseline)

Nepal aimed to graduate from Least Developed Country (LDC) to developing country by 2022 AD.


Indicator

Nepal Status (2015)

LDC Target / Goal

GNI per capita (actual)

USD 659

USD 1,242

Human Asset Index

68.7

66 (threshold)

Economic Vulnerability Index

26.8

32 (threshold)

Infrastructure investment (% GDP)

3-4%

6-7% growth target

Required investment by 2022

-

~Rs. 10,000 billion

 
1.4 Key Challenges

      Enhancing investment and management capacity in infrastructure sector

      Private sector unable to meet time-bound responsibilities (land acquisition, coordination, environmental approval)

      Limited resources and weak professional competence in PPP implementation

      Absence of policy on proper risk-sharing for large national infrastructure projects

      No proper Viability Gap Funding (VGF) arrangement

      Non-transparent project selection process; inadequate feasibility studies

      Lack of independent appraisal practices for feasibility studies

      Persistent security problems and land acquisition difficulties

      Policies not in tune with current international norms and practices

 

Key Fact: Nepal needed approximately Rs. 10,000 billion in investment by 2022 AD to achieve the required growth in infrastructure. Current infrastructure investment of 3-4% of GDP was insufficient; 6-7% annual economic growth was targeted.

 

2. Vision, Goal & Objectives

2.1 Vision

"To ensure public access to infrastructure and services through their qualitative and sustainable development."

2.2 Goal

"To enhance public-private sector investment on development and operation of public infrastructure services through the adoption of the PPP model for comprehensive socio-economic development."

2.3 Objectives (Clause 8)

      8.1 Clause 8.1 - Create environment attracting private investment (domestic and foreign) to meet capital and resource requirements for development, reconstruction and operation of public infrastructure

      8.2 Clause 8.2 - Utilize professionalism, work efficiency, entrepreneurship and technical skills of private sector for qualitative public infrastructure services

3. Policies & Strategies

3.1 Three Core Policies (Clause 9)

      9.1 Policy 9.1 - Promote PPP-related international norms and standards in all feasible state organs and entities

      9.2 Policy 9.2 - Create conducive investment environment for domestic and foreign private sector in infrastructure development

      9.3 Policy 9.3 - Optimal utilization of private sector professionalism, entrepreneurship, ability and latest technologies

3.2 Strategies (Clause 10)

For Policy 9.1 (Clauses 10.1-10.3)

      Accept and adopt prevailing PPP norms in all possible public sectors on basis of necessities and relevance

      Identify and prioritize infrastructure and services implementable under PPP concept

      Make all state organs vibrant as needed to implement PPP projects

For Policy 9.2 (Clauses 10.4-10.6)

      Make procurement and approval processes simple and transparent

      Share risks and benefits between public and private sectors in a justifiable manner

      Ensure GoN investments, cooperation and commitments to implement PPP and boost private sector morale

For Policy 9.3 (Clauses 10.7-10.9)

      Use private sector competence in identification, prioritization, feasibility study and framework preparation

      Utilize professionalism and entrepreneurship of private sector in construction and management

      Ensure accountability of private sector for sustainable operation, repair and maintenance

4. Underlying PPP Principles & Project Forms (Clause 11.1)

4.1 Defining Characteristics of a PPP

      Fixed-period contract between public and private entities

      Private entity bears full or partial financial/construction/operation/maintenance risks

      Private entity provides public services directly or indirectly

      Return on investment through user fees collected over the concession period

      Assets must revert to public entity ownership after the contract period ends

4.2 Salient Features Required (Clause 11.1(5))

      Clearly defined contract period

      Full or partial private capital investment for construction/rehabilitation/modernization

      Private entity responsible for operation, maintenance and service delivery

      Performance-linked payment benchmarks set in advance

      Private entity accepts income-related risk (partly or fully)

      All provisions formalized in a duly signed project agreement

4.3 What Does NOT Constitute a PPP (Clause 11.2(ii))

      Services operated by private sector without transferring financial, technical or operational risks

      Privatization of public assets or liabilities

      Commercialization of public works through government-owned enterprises created by government decision

      Receipt of grants, donations or gifts from private entities for public works

      State security provisions

4.4 Forms of PPP (Spectrum - Minimal to Maximum Private Involvement)

      Management/Operation Contract - private operates public asset, no investment, no risk transfer

      Lease / Concession Agreement - private operates public asset, pays royalty/rent

      Build-Operate-Transfer (BOT) / Build-Own-Operate-Transfer (BOOT)

      Design-Build-Operate-Transfer (DBOT)

      Full private investment with eventual ownership transfer - maximum private involvement

Suitability determined by: project structure, investor/lender acceptability, user fee viability, risk-benefit sharing, and defined agreement period.

4.5 Requirements for Project Implementation (Clause 11.2(i))

      Clear provision on user fees or performance payment mechanism

      Clear allocation of responsibilities between public and private entities

      Risk borne by entity most capable of bearing it

      Detailed service specifications, payment benchmarks, incentives, penalties and grievance mechanisms

      Clarity on ownership of existing and newly created assets

      Effective monitoring system at every level of project cycle

      Result-based payment, motivational incentives and penalty provisions

5. Priority Sectors & Project Identification (Clause 11.3)

5.1 National Priority Sectors

      Physical infrastructure and transportation - Roads, Bridges, Airports, Railways, Cable Cars, Ropeways, all ports

      Electricity sector - Generation, transmission and distribution (together or separately) and other energy types

      Information and communication sector

      Urban and rural environment - Solid waste management, drinking water, sewerage and sanitation

      Education, health infrastructure, and tourism infrastructure (excluding hotels and accommodation)

      Urban amenities

 

Important: Local level PPP projects do NOT require their own specific prioritization list. Techno-economic and market feasibility are the deciding parameters for local level projects (Clause 11.3(3)).

5.2 Project Selection Criteria

      Quality and access to services enhanced

      Current public service status improved

      Economic benefit to Nepalese economy ensured

      Government and local entity funds effectively mobilized

      Innovative and high-level technology utilized

5.3 Project Identification Process (Clause 11.4)

      All public entities identify and determine priority areas; may hold consultation meetings with private sector

      PIAs select, design and assess suitability of PPP projects from identified areas

      PIAs furnish identified projects to National Planning Commission (NPC) for analysis before proceeding

      For projects below Rs. 50 million - chief executive of public entity may formulate own procedures

      Private sector interested in developing a project may be invited to do so (Clause 11.4(4))

6. Project Appraisal & Procurement Process (Clauses 11.6 & 11.7)

6.1 Approval Before Procurement (Clause 11.6)

      Procurement process can only commence after: feasibility study, suitability appraisal, and procurement document approval by competent authority

      PIA submits feasibility study, procurement documents, bidder details and preferred competitor details to approving authority before signing project agreement

      Approving authority may ask PIA to revise project structure or grant approval with mandatory conditions

      Any changes to approved documents or project outlay require fresh approval from competent authority

6.2 Six-Step Procurement Process (Clause 11.7)

Step 1: REOI — Request for Expression of Interest - optional stage to gauge market interest, understand prospective bidders and associated risks

Step 2: RFQ — Request for Qualification - evaluate overall technical and financial competency; prepare shortlist of qualified bidders

Step 3: RFP — Request for Proposal - detailed technical and financial proposals invited from shortlisted bidders only; project agreement draft included

Step 4: Evaluation — Committee (including PPP Centre, NPC and MoF representatives) evaluates proposals on predetermined criteria; technical and financial proposals opened at different times

Step 5: Bid Approval — Preferred bidder's proposal approved by competent authority; notification letter issued

Step 6: Agreement Signing — Project agreement signed; no substantive changes from RFP draft; only minor administrative matters may be amended

6.3 Key RFP Provisions (Clause 11.7(C))

      Project period and specifications clearly stated

      Monitoring process and compensation provisions

      Methods for resolving force majeure, contract termination and scope changes

      VGF and/or equity provisions; royalty/rent/lease charge details

      Risk sharing and management methods during project period

      Infrastructure handover process

      Bid security required with proposal; performance guarantee required before agreement

      Financial proposals opened only for technically qualified bidders

6.4 Unsolicited Proposals (Clause 11.8)

An unsolicited proposal is one not invited by PIA but identified and submitted by an interested private entity.

      Accepted only under three specific conditions:

      (a) Proposals were invited earlier but a successful bidder could not be selected

      (b) Project uses proprietary goods available only with that particular entity

      (c) Council of Ministers declares the project strategically important

      Projects above Rs. 100 million require Council of Ministers approval in principle before proceeding

      If project accepted for processing - PIA invites competitive bids; proposer may also participate

      Proposer has 30 days to match preferred bidder's commitments; if accepted, preferred bidder compensated for bid preparation costs

      If proposer declines or fails to qualify - project not awarded to proposer

7. Key Financial Thresholds

Threshold

Provision

Below Rs. 50 million

Chief executive of public entity may formulate and implement own PPP procedures independently (Cl. 11.4(8))

Below Rs. 100 million

PIA may decide itself whether to seek PPP Centre appraisal; single-stage RFQ+RFP process allowed (Cl. 11.7(2)(a))

Rs. 100 million and above

Mandatory submission to PPP Centre for suitability appraisal; model documents must be used (Cl. 11.6(1)(b))

Rs. 500 million+ OR requires VGF/grants

PPP Board of Directors approval required before commencing procurement (Cl. 11.6(3)(c))

Above Rs. 1 billion

International bids mandatory (Cl. 11.7(2)(d))

Land acquisition

Project agreement cannot be signed unless 80% of required land is acquired by GoN (Cl. 11.9(5))

Unsolicited proposals above Rs. 100 million

Council of Ministers approval in principle required before processing (Cl. 11.8(5))

7.1 Approving Authority Summary

      National-level PIA, below Rs. 500 million, no VGF required - PIA chief executive grants approval

      Rs. 500 million+ and/or requires VGF or government grants - PPP Board of Directors approval required

      Local body, no VGF, no central grant - local body approves and implements independently

      Local body, requires VGF or central government financial support - PPP Board of Directors approval required

      Investment Board Nepal as PIA - follows Investment Board Act; Board of Directors only for VGF/central grant cases

8. Institutional Framework (Chapter 12)

8.1 PPP Board of Directors (Clause 12.1)

      Chairperson: Secretary, Ministry of Finance

      Members: Secretaries of PMO, NPC Secretariat, Home Affairs, Physical Infrastructure & Transport, Land Reform, Forestry, Science/Environment, concerned Ministry, Federal Affairs & Local Development

      Member Secretary: Chief, PPP Centre

Scope of Work

      Provide guidelines on all PPP-related policy matters

      Identify areas and investment opportunities for PPP projects

      Grant approval for procurement process for Rs. 500m+ projects and those requiring VGF

      Establish necessary coordination with concerned entities

8.2 PPP Regulatory Committee (Clause 12.2)

      Chairperson: Secretary, National Planning Commission

      Members: Joint secretaries of MoF, Home Affairs, Physical Infrastructure, Federal Affairs, Land Reform + appointed expert; PPP Centre chief as Member Secretary

      Submits annual report to NPC through infrastructure sector member

      NPC may carry out review and issue necessary directives

8.3 PPP Centre (Clause 12.3)

      Located under National Planning Commission

      Functions: feasibility study and independent suitability appraisal; facilitation of public and private entities; PPP capacity building; domestic and international best practice research; model documents and guidelines; investor/bank coordination; maintain contingent liability records

      Issues model documents: RFQ, RFP and project agreement templates

      Must be consulted before implementing innovative, complex or debut PPP projects

8.4 PIA & PIU (Clause 12.4)

      Every public entity implementing PPP projects = Project Implementing Agency (PIA)

      Each PIA forms a Project Implementation Unit (PIU) per individual project

      PIU responsibilities: preparatory works, studies, procurement, coordination, agreements with private entities, implementation

      Investment Board Nepal: hands approved projects to concerned Ministry after financial closure

9. Financial Provisions (Chapter 13)

9.1 Four Key Financial Instruments

 (a) Project Preparation Facility Fund (PPFF) - Clause 13.4

      Established by Ministry of Finance

      Purpose: feasibility studies, consultancy services, analysis of challenges and opportunities of PPP projects

      Management and mobilization governed by dedicated manual

(b) Revolving Fund for Land Acquisition (RFLA) - Clause 13.5

      Established by Ministry of Finance

      GoN acquires land for PPP projects; costs recoverable from private sector through royalty/rent/lease fee/compensation

      Recovered amounts re-deposited in RFLA (revolving nature)

(c) Viability Gap Fund (VGF) - Clause 13.6

      Established by Ministry of Finance

      Provides direct capital grants to make financially unviable but publicly important projects viable

      Conditions: financial income insufficient to meet expenses AND no adequate alternative funding exists

      Board of Directors decides on VGF grant on recommendation of PPP Centre

      NOT applicable to projects receiving annual installment payments from PIA

(d) Capital Participation - Clause 13.7

      PIAs may invest equity in PPP projects in special cases with clear documented justification

      Bases: enhancing financial viability, strong PIA presence, investor-friendly environment, reasonable project monitoring

9.2 Who Bears Which Costs (Clause 13.10)

      Government: administrative processes (project selection, feasibility study, supervision, expert identification), initial land acquisition costs

      Private sector: all financial obligations related to project implementation

      Public entity: PIU administrative costs

      Land acquisition costs initially by GoN; recoverable from private sector through royalty/rent/lease/reimbursement

      Tax exemption/waiver by GoN permissible depending on project nature (Clause 13.8)

9.3 Budget Provisions (Clause 13.1)

      National level: PIA proposes budget to MoF and NPC; MoF takes final decision in consultation with NPC and PIA

      Local body as PIA: local body council decides budget; included in its budget book

      PPP Centre administrative and other expenses included in every annual budget

10. Risk Sharing, Disputes, Monitoring & Handover

10.1 Risk Sharing Principles (Clause 11.10)

Central Principle: 'Public interest' is kept at the centre. The entity most competent to manage a particular risk should bear that risk. Risk sharing framework based on feasibility study and opportunity analysis.

 

Risk Type

Assigned To

Design, construction, project management quality, technical standards

Private entity

Environmental regulation compliance

Private entity

Cost of service, financial management, fee recovery, profit

Private entity

Permissions, approvals and inter-government coordination

PIA (public entity)

Land acquisition

PIA (public entity)

Government grants-related risks

PIA (public entity)

Force majeure (direct/indirect)

Insurance first; uninsured matters per project agreement

Asset transfer / contract void or cancelled

Adjusted per project agreement; burden depends on cancellation reason

10.2 Land Acquisition (Clause 11.9)

      GoN provides required land to PIA for PPP projects at national and local levels

      GoN follows prevailing land acquisition laws and Land Acquisition, Rehabilitation and Resettlement Policy 2014

      Compensation against land acquisition may be reimbursed through private entity (fully or partly) as stated in procurement documents

      Critical Rule: Project agreement CANNOT be signed unless GoN has acquired 80% of the required land

10.3 Dispute Settlement (Clause 11.12)

      First: Prevailing Nepal laws apply to project agreement

      Second: Amicable settlement through dialogue and discussion between disputing parties

      Third: If amicable settlement fails - Arbitration Act, 1999 applies

      For foreign investors: ICC Rules or UNCITRAL dispute resolution procedure may be adopted (must be stated in project agreement)

      Special projects: separate provisions by Council of Ministers decision as stated in agreement

10.4 Monitoring & Evaluation (Clause 15)

      Primary responsibility: concerned public entity through PIU

      MoF (with PPP Centre) may constitute working committees for financial climate review

      PPP Centre submits annual report to GoN through Board of Directors - must report results achieved and problems faced

      Private entity submits annual audit reports on PPP project income and expenditure to public entity

10.5 Project Handover (Clause 18)

      On contract expiry: private entity hands over physical infrastructure and assets in running condition to PIA

      One year before handover: repair and maintenance under PIA supervision as guided by project documents

      PIA deputes its representatives to oversee the handover process

10.6 Regulatory Provisions (Clause 16)

      GoN constitutes separate sector-specific regulatory bodies

      Regulatory bodies regulate PPP projects

      If no regulatory body exists: regulation based on non-discrimination, independence, transparency and accountability

10.7 Policy Implementation Plan (Clause 11.11)

      This policy acts as the base for formulating Acts, rules, guidelines and manuals

      Within one year of approval: GoN to develop manuals for PPFF and VGF; PPP Centre to issue model documents

      Local bodies to amend the "Public Private Partnership (For Local Bodies) Policy, 2003" on the basis of this policy

11. Quick Reference Summary for Exam

Repeal & Saving (Clause 19): The "Public Infrastructure Construction, Operation and Handover Policy, 2000" is repealed. All actions taken under the 2000 policy are deemed to have been taken under the 2015 policy.

 

11.1 Five Key Numbers to Memorize

      Rs. 50 million - threshold below which PIA chief executive has autonomous authority

      Rs. 100 million - threshold requiring mandatory PPP Centre appraisal and model documents

      Rs. 500 million - threshold requiring PPP Board of Directors approval

      Rs. 1 billion - threshold requiring international bids

      80% - minimum land acquisition by GoN required before signing project agreement

11.2 Key Definitions

      PPP Centre: Under NPC; responsible for appraisal, model documents, capacity building, guidelines

      PIA (Project Implementing Agency): Any public entity implementing a PPP project

      PIU (Project Implementation Unit): Unit formed by PIA per project for implementation

      VGF (Viability Gap Fund): Capital grant to make financially unviable but publicly important projects viable

      Unsolicited Proposal: Proposal not invited by PIA but submitted voluntarily by private entity

      REOI: Request for Expression of Interest (optional, first stage of procurement)

      RFQ: Request for Qualification (Stage 1 - evaluates technical/financial competency, produces shortlist)

      RFP: Request for Proposal (Stage 2 - invites full technical and financial proposals)

11.3 Important Policy Principles

      PPP is a time-bound contract - not permanent privatization

      Assets always revert to public entity after contract period

      Risk borne by entity most capable of managing it

      Public interest is central to all risk/benefit sharing decisions

      Feasibility study and suitability appraisal are mandatory before procurement

      No project agreement can be signed without 80% land acquisition by GoN

      International arbitration (ICC/UNCITRAL) available for foreign investor disputes

      GoN may provide tax exemptions for PPP projects depending on nature and characteristics


These notes are based on the unofficial English translation of Nepal's Public-Private Partnership Policy, 2072 (2015). For official reference, consult the original Nepali version published by the Ministry of Finance, Government of Nepal.