Public-Private Partnership Policy, 2072 (2015)
1. Background, Historical Context & Rationale
1.1 Why PPP
Was Needed
•
National treasury alone insufficient to fund
infrastructure (roads, bridges, airports, railways, electricity, irrigation,
cable cars, drinking water)
•
PPP attracts private sector means, resources, skills and
technology for public development works
•
Private sector contributes: managerial expertise,
innovative technology, and capital investment
•
Goal: make public assets and services less costly,
effective and reliable
1.2
Legislative Timeline
•
2000 AD - "Construction, Operation and Handover of
Public Infrastructure Policy" formulated
•
2006 AD - "Private Sector Investment in the
Construction and Operation of Infrastructure Act" enacted; still in force
• 2015 AD - PPP Policy 2072 (new policy) formulated; repeals the 2000 policy
1.3 Nepal's
Development Status (2015 Baseline)
Nepal aimed to graduate from Least Developed Country (LDC) to developing country by 2022 AD.
|
Indicator |
Nepal
Status (2015) |
LDC
Target / Goal |
|
GNI per
capita (actual) |
USD 659 |
USD 1,242 |
|
Human
Asset Index |
68.7 |
66
(threshold) |
|
Economic
Vulnerability Index |
26.8 |
32
(threshold) |
|
Infrastructure
investment (% GDP) |
3-4% |
6-7% growth
target |
|
Required
investment by 2022 |
- |
~Rs. 10,000
billion |
•
Enhancing investment and management capacity in
infrastructure sector
•
Private sector unable to meet time-bound responsibilities
(land acquisition, coordination, environmental approval)
•
Limited resources and weak professional competence in PPP
implementation
•
Absence of policy on proper risk-sharing for large
national infrastructure projects
•
No proper Viability Gap Funding (VGF) arrangement
•
Non-transparent project selection process; inadequate
feasibility studies
•
Lack of independent appraisal practices for feasibility
studies
•
Persistent security problems and land acquisition
difficulties
• Policies not in tune with current international norms and practices
|
Key Fact: Nepal needed approximately Rs. 10,000 billion in investment
by 2022 AD to achieve the required growth in infrastructure. Current
infrastructure investment of 3-4% of GDP was insufficient; 6-7% annual
economic growth was targeted. |
2. Vision, Goal & Objectives
2.1 Vision
|
"To ensure public access to infrastructure and services through
their qualitative and sustainable development." |
2.2 Goal
|
"To enhance public-private sector investment on development and
operation of public infrastructure services through the adoption of the PPP
model for comprehensive socio-economic development." |
2.3
Objectives (Clause 8)
•
8.1 Clause 8.1 - Create environment attracting private
investment (domestic and foreign) to meet capital and resource requirements for
development, reconstruction and operation of public infrastructure
• 8.2 Clause 8.2 - Utilize professionalism, work efficiency, entrepreneurship and technical skills of private sector for qualitative public infrastructure services
3. Policies & Strategies
3.1 Three
Core Policies (Clause 9)
•
9.1 Policy 9.1 - Promote PPP-related international norms and
standards in all feasible state organs and entities
•
9.2 Policy 9.2 - Create conducive investment environment for
domestic and foreign private sector in infrastructure development
•
9.3 Policy 9.3 - Optimal utilization of private sector
professionalism, entrepreneurship, ability and latest technologies
3.2
Strategies (Clause 10)
For Policy
9.1 (Clauses 10.1-10.3)
•
Accept and adopt prevailing PPP norms in all possible
public sectors on basis of necessities and relevance
•
Identify and prioritize infrastructure and services
implementable under PPP concept
•
Make all state organs vibrant as needed to implement PPP
projects
For Policy
9.2 (Clauses 10.4-10.6)
•
Make procurement and approval processes simple and
transparent
•
Share risks and benefits between public and private
sectors in a justifiable manner
•
Ensure GoN investments, cooperation and commitments to
implement PPP and boost private sector morale
For Policy
9.3 (Clauses 10.7-10.9)
•
Use private sector competence in identification, prioritization,
feasibility study and framework preparation
•
Utilize professionalism and entrepreneurship of private
sector in construction and management
•
Ensure accountability of private sector for sustainable
operation, repair and maintenance
4. Underlying PPP Principles & Project Forms (Clause
11.1)
4.1
Defining Characteristics of a PPP
•
Fixed-period contract between public and private entities
•
Private entity bears full or partial
financial/construction/operation/maintenance risks
•
Private entity provides public services directly or
indirectly
•
Return on investment through user fees collected over the
concession period
• Assets must revert to public entity ownership after the contract period ends
4.2 Salient
Features Required (Clause 11.1(5))
•
Clearly defined contract period
•
Full or partial private capital investment for
construction/rehabilitation/modernization
•
Private entity responsible for operation, maintenance and
service delivery
•
Performance-linked payment benchmarks set in advance
•
Private entity accepts income-related risk (partly or
fully)
•
All provisions formalized in a duly signed project
agreement
4.3 What
Does NOT Constitute a PPP (Clause 11.2(ii))
•
Services operated by private sector without transferring
financial, technical or operational risks
•
Privatization of public assets or liabilities
•
Commercialization of public works through
government-owned enterprises created by government decision
•
Receipt of grants, donations or gifts from private
entities for public works
•
State security provisions
4.4 Forms of
PPP (Spectrum - Minimal to Maximum Private Involvement)
•
Management/Operation Contract - private operates public
asset, no investment, no risk transfer
•
Lease / Concession Agreement - private operates public
asset, pays royalty/rent
•
Build-Operate-Transfer (BOT) / Build-Own-Operate-Transfer
(BOOT)
•
Design-Build-Operate-Transfer (DBOT)
•
Full private investment with eventual ownership transfer
- maximum private involvement
Suitability determined by: project structure,
investor/lender acceptability, user fee viability, risk-benefit sharing, and
defined agreement period.
4.5
Requirements for Project Implementation (Clause 11.2(i))
•
Clear provision on user fees or performance payment
mechanism
•
Clear allocation of responsibilities between public and
private entities
•
Risk borne by entity most capable of bearing it
•
Detailed service specifications, payment benchmarks,
incentives, penalties and grievance mechanisms
•
Clarity on ownership of existing and newly created assets
•
Effective monitoring system at every level of project
cycle
• Result-based payment, motivational incentives and penalty provisions
5. Priority Sectors & Project Identification (Clause
11.3)
5.1
National Priority Sectors
•
Physical infrastructure and transportation - Roads,
Bridges, Airports, Railways, Cable Cars, Ropeways, all ports
•
Electricity sector - Generation, transmission and
distribution (together or separately) and other energy types
•
Information and communication sector
•
Urban and rural environment - Solid waste management,
drinking water, sewerage and sanitation
•
Education, health infrastructure, and tourism
infrastructure (excluding hotels and accommodation)
•
Urban amenities
|
Important: Local level PPP projects do NOT require their own specific
prioritization list. Techno-economic and market feasibility are the deciding
parameters for local level projects (Clause 11.3(3)). |
5.2 Project
Selection Criteria
•
Quality and access to services enhanced
•
Current public service status improved
•
Economic benefit to Nepalese economy ensured
•
Government and local entity funds effectively mobilized
•
Innovative and high-level technology utilized
5.3 Project
Identification Process (Clause 11.4)
•
All public entities identify and determine priority
areas; may hold consultation meetings with private sector
•
PIAs select, design and assess suitability of PPP
projects from identified areas
•
PIAs furnish identified projects to National Planning
Commission (NPC) for analysis before proceeding
•
For projects below Rs. 50 million - chief executive of
public entity may formulate own procedures
• Private sector interested in developing a project may be invited to do so (Clause 11.4(4))
6. Project Appraisal & Procurement Process (Clauses
11.6 & 11.7)
6.1
Approval Before Procurement (Clause 11.6)
•
Procurement process can only commence after: feasibility
study, suitability appraisal, and procurement document approval by competent
authority
•
PIA submits feasibility study, procurement documents,
bidder details and preferred competitor details to approving authority before
signing project agreement
•
Approving authority may ask PIA to revise project
structure or grant approval with mandatory conditions
•
Any changes to approved documents or project outlay
require fresh approval from competent authority
6.2
Six-Step Procurement Process (Clause 11.7)
Step 1: REOI — Request for
Expression of Interest - optional stage to gauge market interest, understand
prospective bidders and associated risks
Step 2: RFQ — Request for
Qualification - evaluate overall technical and financial competency; prepare shortlist
of qualified bidders
Step 3: RFP — Request for Proposal
- detailed technical and financial proposals invited from shortlisted bidders
only; project agreement draft included
Step 4: Evaluation — Committee (including
PPP Centre, NPC and MoF representatives) evaluates proposals on predetermined
criteria; technical and financial proposals opened at different times
Step 5: Bid Approval — Preferred bidder's
proposal approved by competent authority; notification letter issued
Step 6: Agreement Signing — Project agreement
signed; no substantive changes from RFP draft; only minor administrative
matters may be amended
6.3 Key RFP
Provisions (Clause 11.7(C))
•
Project period and specifications clearly stated
•
Monitoring process and compensation provisions
•
Methods for resolving force majeure, contract termination
and scope changes
•
VGF and/or equity provisions; royalty/rent/lease charge
details
•
Risk sharing and management methods during project period
•
Infrastructure handover process
•
Bid security required with proposal; performance
guarantee required before agreement
• Financial proposals opened only for technically qualified bidders
6.4
Unsolicited Proposals (Clause 11.8)
An unsolicited proposal is one not invited by
PIA but identified and submitted by an interested private entity.
•
Accepted only under three specific conditions:
◦
(a)
Proposals were invited earlier but a successful bidder could not be selected
◦
(b)
Project uses proprietary goods available only with that particular entity
◦
(c)
Council of Ministers declares the project strategically important
•
Projects above Rs. 100 million require Council of
Ministers approval in principle before proceeding
•
If project accepted for processing - PIA invites
competitive bids; proposer may also participate
•
Proposer has 30 days to match preferred bidder's
commitments; if accepted, preferred bidder compensated for bid preparation
costs
•
If proposer declines or fails to qualify - project not
awarded to proposer
7. Key Financial Thresholds
|
Threshold |
Provision |
|
Below
Rs. 50 million |
Chief
executive of public entity may formulate and implement own PPP procedures
independently (Cl. 11.4(8)) |
|
Below
Rs. 100 million |
PIA may
decide itself whether to seek PPP Centre appraisal; single-stage RFQ+RFP
process allowed (Cl. 11.7(2)(a)) |
|
Rs. 100
million and above |
Mandatory
submission to PPP Centre for suitability appraisal; model documents must be
used (Cl. 11.6(1)(b)) |
|
Rs. 500
million+ OR requires VGF/grants |
PPP Board
of Directors approval required before commencing procurement (Cl. 11.6(3)(c)) |
|
Above
Rs. 1 billion |
International
bids mandatory (Cl. 11.7(2)(d)) |
|
Land
acquisition |
Project
agreement cannot be signed unless 80% of required land is acquired by GoN
(Cl. 11.9(5)) |
|
Unsolicited
proposals above Rs. 100 million |
Council of
Ministers approval in principle required before processing (Cl. 11.8(5)) |
7.1
Approving Authority Summary
•
National-level PIA, below Rs. 500 million, no VGF
required - PIA chief executive grants approval
•
Rs. 500 million+ and/or requires VGF or government grants
- PPP Board of Directors approval required
•
Local body, no VGF, no central grant - local body
approves and implements independently
•
Local body, requires VGF or central government financial
support - PPP Board of Directors approval required
•
Investment Board Nepal as PIA - follows Investment Board
Act; Board of Directors only for VGF/central grant cases
8. Institutional Framework (Chapter 12)
8.1 PPP
Board of Directors (Clause 12.1)
•
Chairperson: Secretary, Ministry of Finance
•
Members: Secretaries of PMO, NPC Secretariat, Home
Affairs, Physical Infrastructure & Transport, Land Reform, Forestry,
Science/Environment, concerned Ministry, Federal Affairs & Local
Development
•
Member Secretary: Chief, PPP Centre
Scope of
Work
•
Provide guidelines on all PPP-related policy matters
•
Identify areas and investment opportunities for PPP
projects
•
Grant approval for procurement process for Rs. 500m+
projects and those requiring VGF
•
Establish necessary coordination with concerned entities
8.2 PPP
Regulatory Committee (Clause 12.2)
•
Chairperson: Secretary, National Planning Commission
•
Members: Joint secretaries of MoF, Home Affairs, Physical
Infrastructure, Federal Affairs, Land Reform + appointed expert; PPP Centre
chief as Member Secretary
•
Submits annual report to NPC through infrastructure
sector member
•
NPC may carry out review and issue necessary directives
8.3 PPP
Centre (Clause 12.3)
•
Located under National Planning Commission
•
Functions: feasibility study and independent suitability
appraisal; facilitation of public and private entities; PPP capacity building;
domestic and international best practice research; model documents and
guidelines; investor/bank coordination; maintain contingent liability records
•
Issues model documents: RFQ, RFP and project agreement
templates
•
Must be consulted before implementing innovative, complex
or debut PPP projects
8.4 PIA
& PIU (Clause 12.4)
•
Every public entity implementing PPP projects = Project
Implementing Agency (PIA)
•
Each PIA forms a Project Implementation Unit (PIU) per
individual project
•
PIU responsibilities: preparatory works, studies,
procurement, coordination, agreements with private entities, implementation
•
Investment Board Nepal: hands approved projects to
concerned Ministry after financial closure
9. Financial Provisions (Chapter 13)
9.1 Four
Key Financial Instruments
(a) Project Preparation Facility Fund (PPFF) -
Clause 13.4
•
Established by Ministry of Finance
•
Purpose: feasibility studies, consultancy services,
analysis of challenges and opportunities of PPP projects
•
Management and mobilization governed by dedicated manual
(b)
Revolving Fund for Land Acquisition (RFLA) - Clause 13.5
•
Established by Ministry of Finance
•
GoN acquires land for PPP projects; costs recoverable
from private sector through royalty/rent/lease fee/compensation
•
Recovered amounts re-deposited in RFLA (revolving nature)
(c)
Viability Gap Fund (VGF) - Clause 13.6
•
Established by Ministry of Finance
•
Provides direct capital grants to make financially
unviable but publicly important projects viable
•
Conditions: financial income insufficient to meet
expenses AND no adequate alternative funding exists
•
Board of Directors decides on VGF grant on recommendation
of PPP Centre
•
NOT applicable to projects receiving annual installment
payments from PIA
(d) Capital
Participation - Clause 13.7
•
PIAs may invest equity in PPP projects in special cases
with clear documented justification
• Bases: enhancing financial viability, strong PIA presence, investor-friendly environment, reasonable project monitoring
9.2 Who
Bears Which Costs (Clause 13.10)
•
Government: administrative processes (project selection,
feasibility study, supervision, expert identification), initial land
acquisition costs
•
Private sector: all financial obligations related to
project implementation
•
Public entity: PIU administrative costs
•
Land acquisition costs initially by GoN; recoverable from
private sector through royalty/rent/lease/reimbursement
•
Tax exemption/waiver by GoN permissible depending on
project nature (Clause 13.8)
9.3 Budget
Provisions (Clause 13.1)
•
National level: PIA proposes budget to MoF and NPC; MoF
takes final decision in consultation with NPC and PIA
•
Local body as PIA: local body council decides budget;
included in its budget book
• PPP Centre administrative and other expenses included in every annual budget
10. Risk Sharing, Disputes, Monitoring & Handover
10.1 Risk
Sharing Principles (Clause 11.10)
|
Central Principle: 'Public interest' is kept at the centre. The entity
most competent to manage a particular risk should bear that risk. Risk
sharing framework based on feasibility study and opportunity analysis. |
|
Risk
Type |
Assigned
To |
|
Design,
construction, project management quality, technical standards |
Private
entity |
|
Environmental
regulation compliance |
Private
entity |
|
Cost of
service, financial management, fee recovery, profit |
Private
entity |
|
Permissions,
approvals and inter-government coordination |
PIA
(public entity) |
|
Land
acquisition |
PIA
(public entity) |
|
Government
grants-related risks |
PIA
(public entity) |
|
Force
majeure (direct/indirect) |
Insurance
first; uninsured matters per project agreement |
|
Asset
transfer / contract void or cancelled |
Adjusted
per project agreement; burden depends on cancellation reason |
10.2 Land
Acquisition (Clause 11.9)
•
GoN provides required land to PIA for PPP projects at
national and local levels
•
GoN follows prevailing land acquisition laws and Land
Acquisition, Rehabilitation and Resettlement Policy 2014
•
Compensation against land acquisition may be reimbursed
through private entity (fully or partly) as stated in procurement documents
•
Critical Rule: Project agreement CANNOT be signed unless
GoN has acquired 80% of the required land
10.3
Dispute Settlement (Clause 11.12)
•
First: Prevailing Nepal laws apply to project agreement
•
Second: Amicable settlement through dialogue and
discussion between disputing parties
•
Third: If amicable settlement fails - Arbitration Act,
1999 applies
•
For foreign investors: ICC Rules or UNCITRAL dispute
resolution procedure may be adopted (must be stated in project agreement)
•
Special projects: separate provisions by Council of
Ministers decision as stated in agreement
10.4
Monitoring & Evaluation (Clause 15)
•
Primary responsibility: concerned public entity through
PIU
•
MoF (with PPP Centre) may constitute working committees
for financial climate review
•
PPP Centre submits annual report to GoN through Board of
Directors - must report results achieved and problems faced
•
Private entity submits annual audit reports on PPP
project income and expenditure to public entity
10.5
Project Handover (Clause 18)
•
On contract expiry: private entity hands over physical
infrastructure and assets in running condition to PIA
•
One year before handover: repair and maintenance under
PIA supervision as guided by project documents
•
PIA deputes its representatives to oversee the handover
process
10.6
Regulatory Provisions (Clause 16)
•
GoN constitutes separate sector-specific regulatory
bodies
•
Regulatory bodies regulate PPP projects
• If no regulatory body exists: regulation based on non-discrimination, independence, transparency and accountability
10.7 Policy
Implementation Plan (Clause 11.11)
•
This policy acts as the base for formulating Acts, rules,
guidelines and manuals
•
Within one year of approval: GoN to develop manuals for
PPFF and VGF; PPP Centre to issue model documents
• Local bodies to amend the "Public Private Partnership (For Local Bodies) Policy, 2003" on the basis of this policy
11. Quick Reference Summary for Exam
|
Repeal & Saving (Clause 19): The "Public Infrastructure
Construction, Operation and Handover Policy, 2000" is repealed. All
actions taken under the 2000 policy are deemed to have been taken under the
2015 policy. |
11.1 Five
Key Numbers to Memorize
•
Rs. 50 million - threshold below which PIA chief
executive has autonomous authority
•
Rs. 100 million - threshold requiring mandatory PPP
Centre appraisal and model documents
•
Rs. 500 million - threshold requiring PPP Board of
Directors approval
•
Rs. 1 billion - threshold requiring international bids
•
80% - minimum land acquisition by GoN required before
signing project agreement
11.2 Key
Definitions
•
PPP Centre: Under NPC; responsible for appraisal, model
documents, capacity building, guidelines
•
PIA (Project Implementing Agency): Any public entity
implementing a PPP project
•
PIU (Project Implementation Unit): Unit formed by PIA per
project for implementation
•
VGF (Viability Gap Fund): Capital grant to make
financially unviable but publicly important projects viable
•
Unsolicited Proposal: Proposal not invited by PIA but
submitted voluntarily by private entity
•
REOI: Request for Expression of Interest (optional, first
stage of procurement)
•
RFQ: Request for Qualification (Stage 1 - evaluates
technical/financial competency, produces shortlist)
• RFP: Request for Proposal (Stage 2 - invites full technical and financial proposals)
11.3
Important Policy Principles
•
PPP is a time-bound contract - not permanent
privatization
•
Assets always revert to public entity after contract
period
•
Risk borne by entity most capable of managing it
•
Public interest is central to all risk/benefit sharing
decisions
•
Feasibility study and suitability appraisal are mandatory
before procurement
•
No project agreement can be signed without 80% land
acquisition by GoN
•
International arbitration (ICC/UNCITRAL) available for
foreign investor disputes
• GoN may provide tax exemptions for PPP projects depending on nature and characteristics
|
These notes are based on the unofficial English translation of Nepal's
Public-Private Partnership Policy, 2072 (2015). For official reference,
consult the original Nepali version published by the Ministry of Finance,
Government of Nepal. |
